Landscape Refresh Proposal

Presented by the Landscape Special Project Committee

June 2026

Tennis season is now in full swing and we could not be more excited to see the courts filling up with life again. Thank you to every member who makes this club what it is — your energy on and off the court is what drives everything we do. It's with that spirit in mind that the Committee is proud to share this vision for the grounds we all call home.

Executive Summary

The Rothesay Tennis Club has served as a cornerstone of athletic and social life in the Kennebecasis Valley for over a century. As the facility enters its next chapter, the grounds require a comprehensive landscape refresh to match the quality of the Club's courts, programming, and membership experience.

This proposal outlines a landscape renewal plan organized into three priority tiers — Must Have, Should Have, and Nice to Have — covering pathways, lighting, spectator amenities, social gathering spaces, garden areas, and parking improvements. The membership will have the opportunity to vote on which elements to include, and the final scope will be shaped by that input.

Depending on the Club's appetite to invest in infrastructure, the additional cost to each membership ranges from approximately $62 per year for the Must Have scope to $299 per year if all three tiers are included — that's roughly one to five coffees a month under the proposed financing model.

The project is designed for execution beginning Summer 2026, with hardscaping completed in the fall and planting and softscaping finishing by May 2027.

Project Vision

The landscape refresh is guided by three core principles:

Preserve character. Retain the mature trees, heritage charm, and welcoming atmosphere that define the Club. Support competitive play. Improve spectator seating, lighting, and amenities so the Club is better equipped to host tournaments and inter-club events. Build for longevity. Use durable, low-maintenance materials and plantings that reduce long-term operating costs and age gracefully.

Conceptual vision of the refreshed grounds at sunset

Conceptual vision of the refreshed grounds at sunset — fire pit, hedgerow, pathway lighting, and spectator areas.

Preliminary rendering for illustrative purposes only — not a final drawing or plan. Further design refinement to be completed after the broader initiative is voted on and approved.

Current Conditions

The Committee has conducted a detailed walk-through assessment of the property, documenting areas where infrastructure is aging, underperforming, or misaligned with the Club's long-term vision.

Key concerns include cracked and uneven pathways, inadequate lighting along spectator corridors, limited social gathering space, and a rear garden that has become overgrown and underutilized. The existing driveway configuration presents a safety concern, with vehicle traffic passing in close proximity to areas where children and members congregate on foot. The current parking arrangement also creates headlight intrusion on the courts during evening play.

Scope of Work

Scope items have been organized into three priority tiers to guide phasing and investment decisions.

PRIORITY A Must Have $61/member/yr cumulative
A.1

Astroturf — Warm-Up / Play Area

A new synthetic turf surface (1,522 sf) will be installed in the upper grounds area, providing a durable, all-weather warm-up and play space for members. The turf area replaces the existing upper parking lot, eliminating headlight intrusion onto the courts during evening play.

Astroturf — Warm-Up / Play Area

Preliminary rendering for illustrative purposes only — not a final drawing or plan. Further design refinement to be completed after the broader initiative is voted on and approved.

A.2

Site Work, Excavation & Prep

Comprehensive site preparation across pathway and turf areas (3,325 sf), including excavation, grading, subbase installation, and drainage improvements to ensure a stable foundation for all new surfaces.

A.3

Pathway Lighting

A comprehensive low-voltage LED landscape lighting system will be installed along all primary pathways, the spectator corridor, and key gathering areas. Fixtures will include bollard-style path lights, recessed step lights at grade changes, and accent uplighting on feature plantings and trees. The system will operate on automatic timers with seasonal adjustment.

Pathway Lighting

Preliminary rendering for illustrative purposes only — not a final drawing or plan. Further design refinement to be completed after the broader initiative is voted on and approved.

A.4

Gravel Pathways

All primary and secondary pathways (1,803 sf) throughout the grounds will be replaced with new gravel surfaces. The pathway system will provide accessible, well-graded connections between the parking area, clubhouse entrance, spectator areas, and rear garden.

A.5

Irrigation — Turf Area

An irrigation system will be installed to serve the new turf area (1,522 sf), ensuring healthy establishment and long-term maintenance of the synthetic playing surface.

PRIORITY B Should Have $206/member/yr cumulative
B.1

Site Work — Hardscape and Lawn Areas

Site preparation, excavation, and grading across all hardscaping and lawn areas (9,054 sf), including subbase work for stone surfaces, deck foundations, and lawn bed preparation.

B.2

Irrigation — Lawn / Sod Areas

An irrigation system serving all lawn and sod areas (7,592 sf) to support healthy turf establishment and reduce long-term maintenance burden.

B.3

Stone Steps & Handrail

New stone steps with integrated handrails will be installed at key grade changes around the clubhouse and spectator areas, improving safety and accessibility across the grounds.

Stone Steps & Handrail

Preliminary rendering for illustrative purposes only — not a final drawing or plan. Further design refinement to be completed after the broader initiative is voted on and approved.

B.4

Hardscaping

New hardscaped surfaces (1,462 sf) around the clubhouse surrounds, including patios, terraces, and gathering areas. Materials will be selected for durability and to complement the existing clubhouse architecture.

Hardscaping

Preliminary rendering for illustrative purposes only — not a final drawing or plan. Further design refinement to be completed after the broader initiative is voted on and approved.

B.5

Grass / Sod — Lawn Areas

All lawn areas (7,592 sf) will be re-sodded with a robust turf product, including the area currently occupied by the upper driveway which will be converted to green space.

B.6

Bleachers × 3 Locations

New bleacher seating will be installed at three locations along the courts, providing additional spectator capacity. Access to the proposed new bleacher areas will be evaluated during detailed design.

Bleachers × 3 Locations

Preliminary rendering for illustrative purposes only — not a final drawing or plan. Further design refinement to be completed after the broader initiative is voted on and approved.

B.7

Planting — Rear Garden Beds

The existing rear garden will be fully removed and replaced with new perennial beds, ornamental grasses, and flowering shrubs (480 sf) selected for four-season interest and low maintenance.

Planting — Rear Garden Beds

Preliminary rendering for illustrative purposes only — not a final drawing or plan. Further design refinement to be completed after the broader initiative is voted on and approved.

PRIORITY C Nice to Have $298/member/yr cumulative
C.1

Warm-Up Area

A dedicated warm-up and stretching area adjacent to the courts, designed for pre-match preparation and casual use.

C.2

Hedge / Fence — East Property Line

A 70 linear foot hedge or fence along the East property line adjacent to the turf area, providing privacy screening and a defined boundary.

C.3

Fire Pit

A built fire pit with a natural stone or brick surround will be installed on the lower lawn area, creating a central gathering point for post-match socializing and club events.

Fire Pit

Preliminary rendering for illustrative purposes only — not a final drawing or plan. Further design refinement to be completed after the broader initiative is voted on and approved.

C.4

Storage Shed

A new dedicated storage facility will be constructed to house court maintenance equipment, event supplies, and seasonal items.

C.5

Outdoor Furniture

New outdoor furniture and furnishings for spectator areas, the rear terrace, and social gathering spaces.

Project Schedule

Board approval and financing will be completed by June 15. Detailed design and town coordination begin immediately after, running six weeks through August. Tendering, approvals, and procurement follow in September. Site work and hardscaping begin in October and continue through the end of the year. Planting, softscaping, and commissioning follow in Spring 2027, with full completion targeted for May 2027.

Activity
MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY
Board Approval & Financing (by June 15)
Detailed Design (6 weeks)
Town Coordination
Tendering, Approvals & Procurement (4 weeks)
Site Work & Hardscaping
Planting, Softscaping & Commissioning

Budget Summary

Cost estimates are derived from a proportional area takeoff using a blended rate of $26 per square foot, organized by priority tier.

PRIORITY A Must Have — $61/member/yr $79,240
Astroturf — warm-up / play area (1,522 sf × $19/sf)
$28,908
Site work, excavation & prep — pathways and turf (3,325 sf × $5/sf)
$16,625
Lighting — pathways and grounds
$15,000
Irrigation — turf area (1,522 sf × $4/sf)
$6,086
Gravel pathways (1,803 sf × $7/sf)
$12,621
PRIORITY B Should Have — $206/member/yr $136,460
Site work, excavation & prep — hardscape and lawn (9,054 sf × $3.50/sf)
$31,689
Irrigation — lawn / sod areas (7,592 sf × $3/sf)
$22,775
Stone steps & handrail
$22,000
Hardscaping (1,462 sf × $14/sf)
$20,470
Grass / sod — lawn areas incl. driveway (7,592 sf × $2.75/sf)
$20,888
Bleachers and associated hardscaping × 3 locations
$10,000
Planting — rear garden beds (480 sf × $18/sf)
$8,638
PRIORITY C Nice to Have — $298/member/yr $86,500
Warm-up area
$29,500
Hedge / fence — East property line (70 LF × $250/LF)
$17,500
Fire pit
$15,000
Storage shed
$15,000
Outdoor furniture
$9,500
Priority A: Must Have
$79,240
$61/member/yr cumulative
Priority B: Should Have
$136,460
$206/member/yr cumulative
Priority C: Nice to Have
$86,500
$298/member/yr cumulative
Hard Costs
$302,200
Soft Costs & Contingency (20%)
$60,440
Total Investment
$362,640

Priority Vote

Help shape the final project scope. Vote on which Should Have and Nice to Have items matter most to you. One vote per member. Results are anonymous and updated in real time.

--
Days
--
Hours
--
Minutes
--
Seconds
Priority B — Should Have
Site work, excavation & prep — hardscape and lawn (9,054 sf × $3.50/sf)
$31,689
Irrigation — lawn / sod areas (7,592 sf × $3/sf)
$22,775
Stone steps & handrail
$22,000
Hardscaping (1,462 sf × $14/sf)
$20,470
Grass / sod — lawn areas incl. driveway (7,592 sf × $2.75/sf)
$20,888
Bleachers and associated hardscaping × 3 locations
$10,000
Planting — rear garden beds (480 sf × $18/sf)
$8,638
Priority C — Nice to Have
Warm-up area
$29,500
Hedge / fence — East property line (70 LF × $250/LF)
$17,500
Fire pit
$15,000
Storage shed
$15,000
Outdoor furniture
$9,500

Enter your email to cast your vote

Funding Strategy

The following scenario demonstrates how the investment could be structured, assuming 150 memberships and current market interest rates.

Scenario A

Club Funds + Financing

Up to $25,000 is drawn from available club funds to cover soft costs (landscape architect, permits, consultants). The remaining $337,640 is financed through a 10-year term loan at an assumed rate of 5.5%. Estimated annual debt service is approximately $45,000, or roughly $299 per membership per year.

Memorial and Dedication Program

The Committee recommends establishing a Memorial and Dedication Program that allows members and families to honour loved ones through named elements within the landscape. Contributions offset project costs while creating lasting, personal connections to the Club grounds.

Dedication ElementContribution
Pathway stone — engraved paver or flagstone$250
Garden bed plaque — bronze or stone marker$500
Bench or bleacher dedication$1,000
Fire pit surround — engraved stone on perimeter$2,500
Hedge wall section — dedicated planting with marker$2,500
Viewing deck or pavilion naming$10,000 – $25,000

As an illustration, 30 pathway stones, 20 garden plaques, 10 bench dedications, and 4 fire pit or hedge dedications would raise approximately $37,500. A single pavilion naming gift could bring the total to $50,000–$60,000 or more. If contributions exceed the base scope, surplus funds would be directed toward a future addition: a bubbling water feature with names inscribed on natural stone, creating a centrepiece for quiet reflection within the rear garden.

Design & Validation Partners

The Committee has requested design proposals from established landscape architecture firms with deep roots in New Brunswick, and project costs have been independently validated by a local pre-construction specialist. After reviewing submissions, the Committee is recommending Brackish Design Studio based on their close proximity to the Club, their expressed interest in becoming Club members, and the strength of their experience, credentials, and body of work across Atlantic Canada.

Brackish Design Studio

Saint John & Halifax  ·  Landscape Architecture  ·  Design proposal requested

Founded in 2019 by landscape architects Matthew Brown and Sandra Cooke, Brackish is a place-based design studio that celebrates the character of Atlantic Canada's landscapes. Operating from offices in Saint John and Halifax, the firm brings a thoughtful, site-sensitive approach to every project — designing outdoor spaces that feel like they belong exactly where they are. Members of the Ontario Association of Landscape Architects (OALA).

Glenn Group Ltd

Fredericton, NB  ·  Landscape Architecture & Planning  ·  Design proposal requested

A full-service landscape architectural practice founded in 2007 by Daniel K. Glenn and headquartered at 248 Brunswick Street, Fredericton. With a motto of "be sustainable, be efficient, be creative," the firm has completed over 500 master plan developments across Atlantic Canada, specializing in parks, tourism destinations, and recreational facilities — making them a natural fit for a project of this scale.

Brott Development Group

Project Cost Validation

A pre-construction budgeting and project management firm with nearly two decades of experience working alongside premier builders and architects. Brott Development Group has independently validated the cost estimates presented in this proposal, providing the Committee with confidence that the budget figures are realistic, market-aligned, and achievable.

Next Steps

The Board respectfully requests that the membership review this proposal and provide direction at the upcoming Annual General Meeting. The following resolution will be presented for a vote:

"Be it resolved that the Board of Directors of the Rothesay Tennis Club is authorized to proceed with the Landscape Refresh as described in the proposal dated June 2026, to allocate up to $362,640 from approved funding sources including capital reserves, member levy, grants, and financing, and to engage qualified contractors through a competitive tendering process for work to commence in Summer 2026, with completion targeted for May 2027."

If approved, the Board will immediately proceed with:

Financing and FundingMay – June 2026

  • Approve funding scenario
  • Obtain loan pre-approval from the Club's bank

Club VoteJune 2026

Design and TenderingJune – September 2026

  • Engage a landscape architect for detailed design drawings and specifications
  • Issue RFP to qualified contractors; evaluate bids
  • Present recommended contractor and final budget to the Board

Town CoordinationJune – August 2026

  • Initiate discussions with the Town regarding lower-level parking access
  • Coordinate driveway and road access permits as required

Execution and OversightOctober 2026 – May 2027

  • Construction to begin following final Board approval
  • Monthly progress updates; sponsorship and naming outreach in parallel

Haven't voted yet? Share your preferences above ↑

Respectfully submitted by the Landscape Special Project Committee

Hilary Brock | Penny Buck | Mary Ann Gallagher
Paul Harrs | Gerry Sparkes | Benjamin Brott

Rothesay Tennis Club — June 2026